Home
Our Vision
Community
Life at Vose Farm
Energy Conservation and Sustainability
Neighborhood
Apartments
Floor Plans
Amenities
FAQs
About Us
News
Contact Us
October Updates
Week of 10/29/24: Elevator Foundation and Pit
Week of 10/29/24: Front entrance from inside looking out
Week of 10/29/24: Front entrance looking in towards building
Week of 10/29/24: Site grading and prep for paving
Week of 10/29/24: Slab prevention and grading
Week of 10/29/24: Under slab utilities and grading
Week of 10/29/24: Underground electrical stubbed up to electrical room
Week of 10/29/24: Underslab utilities stubbed for future connections
Week of 10/15/24: Foundation walls backfilled and starting underslab work
Week of 10/15/24: Site grading underway at back of site
Week of 10/15/24: Site grading underway at front of site
Week of 10/15/24: Material being moved to prepare for underslab work
Week of 10/8/24: Underground plumbing connections into the site
Week of 10/8/24: Damp proof coating being applied
Week of 10/8/24: Hydroseeding of retention pond area
Week of 10/8/24: Rebar install for foundation walls